Schedule of building project

2015

 June Groundbreaking in Lengnaumoos

 Groundbreaking: June 2015

 

Foundation stone ceremony: May 2016

2016- 2017

 

 

 

January - March

Staking

February - April

Excavation

May

Foundation stone ceremony in Lengnaumoos

from May

Construction (structural work)

Interior work / manufacturing plant / infrastructure

2017-2018

 

Testing / qualification

2018-2019

 

Engineering runs / process-validations

 

2020

 

Submissions to Swissmedic & FDA
Inspections by Swissmedic & FDA

Approval and start production

 

Topping out ceremony: February 2017

 

 