14.11.2011:
First meeting
02.07.2012:
Reduction of sites
17.10.2013:
2. reduction of sites
22.05.2014:
Location decision
24.06.2014:
Decision of the Executive Council of Bern
22.08.2014:
Start participation process
28.08.2014:
1. Information event and participation procedure in Lengnau
04.11.2014:
Filing building application
13.11.2014:
2. Information event
08.01.2015:
Publication building application
02.03.2015:
Appointment of Senior Vice President and Managing Director
04.03.2015:
3. Information event
30.04.2015:
Building permit granted
17.06.2015:
1. premature construction start
29.06.2015:
Confirmation building permit
30.06.2015:
Groundbreaking
05.10.2015:
2. premature construction start
30.10.2015:
Appeal to the Federal Supreme Court of Switzerland
30.11.2015:
4. Information event
22.12.2015:
Decision of the Swiss Federal Supreme Court
29.01.2016:
CA approval factor IX
07.03.2016:
FDA approval factor IX
14.04.2016:
From a bird's-eye view
03.05.2016:
Time capsule
03.05.2016:
Foundation stone ceremony video (in German)
03.05.2016:
Laying of foundation stone
12.05.2016:
EU approval factor IX
26.05.2016:
FDA approval factor VIII
01.07.2016:
Batton change
28.09.2016:
Report on SRF News
30.09.2016:
TGA & MHLW approval factor IX
05.10.2016:
Foundation construction
15.10.2016:
Architecture
18.10.2016:
5. Information Event & Pressday
20.10.2016:
Product development and status construction work
31.10.2016:
Requirements of interior work
12.12.2016:
Health Canada approval factor VIII
02.02.2017:
Topping out ceremony video
02.02.2017:
Topping out ceremony
22.03.2017:
Interview Telebielingue
29.11.2017:
Name disclosure